Accepted programme
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is identified within the Contract Data.
The contractor prepares a programme for the works, which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use. Ref. NEC Dictionary.
The contract may also require that a revised programme is prepared regularly, setting out the sequence of activities, progress, and the effect of compensation events. This must then be submitted to the project manager, and if accepted, this becomes the accepted programme, sometimes referred to as the updated programme. The final updated programme will show the as-built programme.
Within the ECC, the ‘activity schedule’ allocates a price to each activity undertaken during the works. This simplifies the administration of the interim payment process. The accepted programme shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date.
Without an accepted programme the contract cannot be administered properly. Under such circumstances, 25% of payments can be withheld, and it is not possible to assess compensation events.
Accepting the programme does not discharge the contractor of any responsibility, it simply accepts that the programme is realistic and that it can be used to assess future changes. If the programme is not accepted by the project manager, reasons for not accepting it must be given.
Reasons might include:
- It is not practical.
- It does not show required information.
- It does not properly represent the actual programme for activities.
- It does not show the full works.
Failure to accept or reject a programme may constitute a compensation event.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether the programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Baseline programme.
- Compensation event.
- Contract conditions.
- Contract data.
- Contractor's master programme.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme.
- Programme for building design and construction.
- Programme narrative.
- Progress in construction.
- Short period programme.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
- Z clauses.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.